The following provides a description of the updates that have been made to the Aspen at Melford schedule with a data date of 03/10/2023:

Completed this past month:

  • Masonry veneer completed and lap siding progressed at Building A1
  • Drywall, paint, tile, and door installation progressed at Building A1
  • Cabinets were delivered for Building A1
  • Gypcrete was poured on the upper levels of Building A1
  • Masonry veneer & lap siding progressed at Building A2
  • Insulation and drywall progressed at Building A2
  • Wood framing progressed at Buildings C & D
  • The plaza & south courtyard areas were cleared out for site work to begin
  • Storefront windows installed in amenity areas

Upcoming this month:

  • Lap siding will complete at Building A1 Cabinets, countertops, light fixtures, and plumbing fixtures will begin to be installed on lower levels of Building A1
  • Masonry veneer and lap siding will completed at Building A2
  • Insulation and drywall will complete at Building A2
  • Paint, tile, and doors will begin at Building A2
  • Wood framing will complete at Buildings C & D
  • MEP rough-ins will begin in Building C
  • Site work will begin in the south courtyard and plaza areas Insulation and drywall will progress in amenity areas